Wingate Park Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball courts at Wingate Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018
Completion Date: September 2019

Construction

Start Date: October 2019
Projected Completion Date: October 2020
Completion Date: January 2021

Understand how we build parks.

Funding

Total Funding: $2,203,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Wingate Park, Brooklyn
Winthrop Street between Brooklyn Avenue and Kingston Avenue
Community Board: 09

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024