Wingate Park Basketball Courts Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the basketball courts at Wingate Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2017
Projected Completion Date:
March 2018
Completion Date:
March 2018
Procurement
Start Date: March 2018
Projected Completion Date:
December 2018
Completion
Date:
September 2019
Construction
Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date: January 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Wingate Park, Brooklyn
Winthrop Street between Brooklyn Avenue and Kingston Avenue
Community Board: 09
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024