Wagner Playground Synthetic Turf Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the combination soccer and baseball synthetic turf field and adjacent fencing, drinking fountains, and seating areas at Wagner Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: December 2019

Construction

Start Date: March 2020
Projected Completion Date: March 2021
Completion Date: January 2021

Understand how we build parks.

Funding

Total Funding: $1,765,000
Funding Source: Mayoral

Location

Wagner Playground, Manhattan
Second Avenue between East 120th Street and East 121st Street
Community Board: 11

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024