Abraham Lincoln Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building in Abraham Lincoln Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2017
Projected Completion Date: February 2018
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: March 2019

Construction

Start Date: September 2019
Projected Completion Date: March 2021
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $1,640,000
Funding Source: Mayoral

Location

Abraham Lincoln Playground, Manhattan
Fifth Avenue and East 135th Street
Community Board: 11

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project