Abraham Lincoln Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building in Abraham Lincoln Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2017
Projected Completion Date:
February 2018
Completion Date:
January 2018
Procurement
Start Date: January 2018
Projected Completion Date:
October 2018
Completion
Date:
March 2019
Construction
Start Date: September 2019
Projected Completion Date:
March 2021
Completion Date: May 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Abraham Lincoln Playground, Manhattan
Fifth Avenue and East 135th Street
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024