Midland Beach Landscape and Drainage Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Hurricane Sandy-damaged drain inlets, catch basins and lines, timber barrier rail fencing, vehicular barrier gates (and concrete island) and electrical utility boxes at Midland Beach.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2015
Projected Completion Date: April 2016
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: April 2018
Completion Date: May 2018

Construction

Start Date: June 2018
Projected Completion Date: June 2019
Completion Date: May 2019

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Franklin D. Roosevelt Boardwalk and Beach, Staten Island
Father Capodanno Boulevard between Iona Street and Elm Tree Boulevard
Community Board: 02

 