Midland Beach Landscape and Drainage Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Hurricane Sandy-damaged drain inlets, catch basins and lines, timber barrier rail fencing, vehicular barrier gates (and concrete island) and electrical utility boxes at Midland Beach.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2015
Projected Completion Date:
April 2016
Completion Date:
August 2017
Procurement
Start Date: August 2017
Projected Completion Date:
April 2018
Completion
Date:
May 2018
Construction
Start Date: June 2018
Projected Completion Date:
June 2019
Completion Date: May 2019
Understand how we build parks.
Funding
Location
Franklin D. Roosevelt Boardwalk and Beach, Staten Island
Father Capodanno Boulevard between Iona Street and Elm Tree Boulevard
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024