5 Boro Complex and Garage Parking Lot Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the parking lot at the 5 Boro Complex and Garage on Randall's Island.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: December 2016
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: June 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $1,732,000
Funding Source: Mayoral

Location

Randall's Island Park, Manhattan
20 Bronx Shore Road
Community Board: 11

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024