5 Boro Complex and Garage Parking Lot Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the parking lot at the 5 Boro Complex and Garage on Randall's Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
December 2016
Completion Date:
April 2018
Procurement
Start Date: April 2018
Projected Completion Date:
January 2019
Completion
Date:
June 2019
Construction
Start Date: July 2019
Projected Completion Date:
July 2020
Completion Date: October 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Randall's Island Park, Manhattan
20 Bronx Shore Road
Community Board: 11
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024