Newport Playground Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building in Newport Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2016
Projected Completion Date: March 2017
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018
Completion Date: June 2018

Construction

Start Date: February 2019
Projected Completion Date: August 2020
Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $929,000
Funding Source: Mayoral

Location

Newport Playground, Brooklyn
Riverdale Avenue between Osborn Street and Thatford Avenue
Community Board: 16

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025