Newport Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building in Newport Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2016
Projected Completion Date:
March 2017
Completion Date:
July 2017
Procurement
Start Date: July 2017
Projected Completion Date:
April 2018
Completion
Date:
June 2018
Construction
Start Date: February 2019
Projected Completion Date:
August 2020
Completion Date: November 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Newport Playground, Brooklyn
Riverdale Avenue between Osborn Street and Thatford Avenue
Community Board: 16
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025