MacArthur Park Multi-Purpose Ballfield and Basketball Court Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the existing ballfields, basketball courts, and sports lighting, and improve the edges and entrances at MacArthur Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
October 2017
Completion Date:
February 2018
Procurement
Start Date: February 2018
Projected Completion Date:
November 2018
Completion
Date:
March 2019
Construction
Start Date: April 2019
Projected Completion Date:
October 2020
Completion Date: May 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Federal
- Mayoral
Location
Gen. Douglas MacArthur Park, Staten Island
Jefferson Street between Dongan Hills Avenue and Seaver Avenue
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 01/17/2025