MacArthur Park Multi-Purpose Ballfield and Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the existing ballfields, basketball courts, and sports lighting, and improve the edges and entrances at MacArthur Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: February 2018

Procurement

Start Date: February 2018
Projected Completion Date: November 2018
Completion Date: March 2019

Construction

Start Date: April 2019
Projected Completion Date: October 2020
Completion Date: May 2021

Understand how we build parks.

Funding

Total Funding: $8,972,000
Funding Sources:
  • Borough President
  • Federal
  • Mayoral

Location

Gen. Douglas MacArthur Park, Staten Island
Jefferson Street between Dongan Hills Avenue and Seaver Avenue
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/11/2024