Arden Woods Trailhead Parking Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct an off-street parking lot and trailhead at Arden Woods.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2016
Projected Completion Date:
March 2018
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
September 2019
Completion
Date:
March 2021
Construction
Start Date: April 2021
Projected Completion Date:
April 2022
Completion Date: November 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
Location
Arden Woods, Staten Island
Arden Avenue between Kyle Court and Forest Green
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024