Arden Woods Trailhead Parking Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct an off-street parking lot and trailhead at Arden Woods.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2016
Projected Completion Date: March 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: April 2022
Completion Date: November 2021

Understand how we build parks.

Funding

Total Funding: $1,238,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Arden Woods, Staten Island
Arden Avenue between Kyle Court and Forest Green
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024