DeLury Square Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct DeLury Square.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2017
Projected Completion Date: November 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019
Completion Date: October 2019

Construction

Start Date: February 2020
Projected Completion Date: November 2020
Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $303,000
Funding Sources:
  • City Council
  • Mayoral

Location

DeLury Square, Manhattan
Fulton Street between Gold and Cliff Streets
Community Board: 01

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024