P.S. 155 Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct P.S. 155 Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2019
Projected Completion Date:
November 2020
Completion Date:
April 2021
Procurement
Start Date: April 2021
Projected Completion Date:
January 2022
Completion
Date:
January 2023
Construction
Start Date: March 2023
Projected Completion Date:
March 2024
Completion Date: January 2024
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
P.S. 155 Playground, Manhattan
East 117th Street and East 118th Street between 1st Avenue and 2nd Avenue
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025