P.S. 155 Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct P.S. 155 Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2019
Projected Completion Date: November 2020
Completion Date: April 2021

Procurement

Start Date: April 2021
Projected Completion Date: January 2022
Completion Date: January 2023

Construction

Start Date: March 2023
Projected Completion Date: March 2024
Completion Date: January 2024

Understand how we build parks.

Funding

Total Funding: $3,185,000
Funding Sources:
  • Borough President
  • City Council

Location

P.S. 155 Playground, Manhattan
East 117th Street and East 118th Street between 1st Avenue and 2nd Avenue
Community Board: 11

 