Flushing Meadows Corona Park Pool Emergency Roof Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the roof at the Flushing Meadows Corona Park Pool.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2016
Completion Date:
January 2017
Procurement
Start Date: January 2017
Projected Completion Date:
October 2017
Completion
Date:
July 2017
Construction
Start Date: May 2017
Projected Completion Date:
February 2018
Completion Date: October 2017