Bay Terrace Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the lower entrance, handball court, basketball court, and multipurpose play area at Bay Terrace Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: April 2019

Procurement

Start Date: April 2019
Projected Completion Date: January 2020
Completion Date: May 2021

Construction

Start Date: October 2021
Projected Completion Date: October 2022
Completion Date: June 2023

Understand how we build parks.

Funding

Total Funding: $3,270,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Bay Terrace Playground, Queens
23rd Avenue between Bell Boulevard and 212th Street
Community Board: 07

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024