Bay Terrace Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the lower entrance, handball court, basketball court, and multipurpose play area at Bay Terrace Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2018
Projected Completion Date:
April 2019
Completion Date:
April 2019
Procurement
Start Date: April 2019
Projected Completion Date:
January 2020
Completion
Date:
May 2021
Construction
Start Date: October 2021
Projected Completion Date:
October 2022
Completion Date: June 2023
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Bay Terrace Playground, Queens
23rd Avenue between Bell Boulevard and 212th Street
Community Board: 07
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024