Travers Park Tot Lot Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

The project will reconstruct the tot lot in Travers Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: April 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $1,536,000
Funding Source: Borough President

Location

Travers Park, Queens
78th Street between Northern Boulevard and 34th Avenue
Community Board: 03

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024