Travers Park Tot Lot Reconstruction
-
100% complete
-
100% complete
-
100% complete
The project will reconstruct the tot lot in Travers Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
June 2018
Completion Date:
June 2018
Procurement
Start Date: June 2018
Projected Completion Date:
March 2019
Completion
Date:
April 2019
Construction
Start Date: August 2019
Projected Completion Date:
August 2020
Completion Date: October 2020
Understand how we build parks.
Funding
Funding Source: Borough President
Location
Travers Park, Queens
78th Street between Northern Boulevard and 34th Avenue
Community Board: 03
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025