Nelson Playground Basketball Court and Bleachers Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball court and bleachers at Nelson Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2017
Projected Completion Date: December 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: July 2018

Construction

Start Date: August 2018
Projected Completion Date: August 2019
Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $354,000
Funding Source: City Council

Location

Nelson Playground, Bronx
West 166th Street between Woodycrest Avenue and Nelson Avenue
Community Board: 04

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024