Nelson Playground Basketball Court and Bleachers Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the basketball court and bleachers at Nelson Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2017
Projected Completion Date:
December 2017
Completion Date:
December 2017
Procurement
Start Date: December 2017
Projected Completion Date:
September 2018
Completion
Date:
July 2018
Construction
Start Date: August 2018
Projected Completion Date:
August 2019
Completion Date: December 2018
Understand how we build parks.
Funding
Funding Source: City Council
Location
Nelson Playground, Bronx
West 166th Street between Woodycrest Avenue and Nelson Avenue
Community Board: 04
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024