Cunningham Park Garage Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the garage in Cunningham Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2018
Projected Completion Date: February 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: September 2021
Completion Date: August 2024

Construction

Start Date: November 2024
Projected Completion Date: May 2026

Understand how we build parks.

Funding

Total Funding: $26,760,000
Funding Source: Mayoral

Location

Cunningham Park, Queens
Union Turnpike and 199th Street
Community Board: 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025