Cunningham Park Garage Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the garage in Cunningham Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2018
Projected Completion Date: February 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: September 2021
Completion Date: August 2024

Construction

Start Date: November 2024
Projected Completion Date: May 2026

Understand how we build parks.

Funding

Total Funding: $26,760,000
Funding Source: Mayoral

Location

Cunningham Park, Queens
Union Turnpike and 199th Street
Community Board: 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024