Lt. Federico Narvaez Tot Lot Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct new play equipment for 2-5 years old, benches, fencing, drainage and water supply systems and plantings in Lt. Federico Narvaez Tot Lot.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
October 2017
Completion Date:
November 2017
Procurement
Start Date: November 2017
Projected Completion Date:
August 2018
Completion
Date:
December 2019
Construction
Start Date: March 2020
Projected Completion Date:
March 2021
Completion Date: March 2021
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Lt. Federico Narvaez Tot Lot, Brooklyn
Argyle Road between Cortelyou Road and Dorchester Road
Community Board: 14
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024