Homecrest Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the children's play area in Homecrest Playground, including the spray shower, play equipment, paving, site furniture, landscaping and utilities.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: September 2019

Construction

Start Date: October 2019
Projected Completion Date: October 2020
Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $3,375,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Homecrest Playground, Brooklyn
Williams Court, East 14th Street, Homecrest Avenue, Shore Parkway
Community Board: 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024