East River Esplanade Reconstruction, East 68th-70th Streets

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the East River Esplanade from East 68th Street to East 70th Street.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: July 2019

Procurement

Start Date: July 2019
Projected Completion Date: April 2020
Completion Date: April 2021

Construction

Start Date: May 2021
Projected Completion Date: May 2022
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $1,859,000
Funding Sources:
  • City Council
  • Mayoral

Location

East River Walk, Manhattan
between the East River and FDR Drive, East 68th Street to East 70th Street
Community Board: 08

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024