McKinley Playground Play Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and spray shower, including fencing, paving, curbs, safety surfacing, benches, lighting, play equipment, plantings, and trees at McKinley Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019
Completion Date: January 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $2,916,000
Funding Sources:
  • Borough President
  • City Council
  • Private

Location

McKinley Playground, Manhattan
East 3rd Street, East 4th Street, Avenue A, 1st Avenue
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024