McKinley Playground Play Area Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground and spray shower, including fencing, paving, curbs, safety surfacing, benches, lighting, play equipment, plantings, and trees at McKinley Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
June 2018
Completion Date:
November 2018
Procurement
Start Date: November 2018
Projected Completion Date:
August 2019
Completion
Date:
January 2020
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: September 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Private
Location
McKinley Playground, Manhattan
East 3rd Street, East 4th Street, Avenue A, 1st Avenue
Community Board: 03
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024