Dag Hammarskjold Plaza Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    5% complete

This project will reconstruct Dag Hammarskjold Plaza including the fences, benches, pavements, trees, planting beds lighting for art stage lighting.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: September 2022

Procurement

Start Date: September 2022
Projected Completion Date: February 2019
Completion Date: December 2023

Construction

Start Date: June 2024
Projected Completion Date: June 2025

Understand how we build parks.

Funding

Total Funding: $1,557,000
Funding Source: City Council

Location

Dag Hammarskjold Plaza, Manhattan
East 47th Street between First Avenue and Second Avenue
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/11/2024