Dag Hammarskjold Plaza Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    8% complete

This project will reconstruct Dag Hammarskjold Plaza including the fences, benches, pavements, trees, planting beds lighting for art stage lighting.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: September 2022

Procurement

Start Date: September 2022
Projected Completion Date: February 2019
Completion Date: December 2023

Construction

Start Date: June 2024
Projected Completion Date: June 2025

Understand how we build parks.

Funding

Total Funding: $1,557,000
Funding Source: City Council

Location

Dag Hammarskjold Plaza, Manhattan
East 47th Street between First Avenue and Second Avenue
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025