Dag Hammarskjold Plaza Reconstruction
-
100% complete
-
100% complete
-
5% complete
This project will reconstruct Dag Hammarskjold Plaza including the fences, benches, pavements, trees, planting beds lighting for art stage lighting.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2017
Projected Completion Date:
May 2018
Completion Date:
September 2022
Procurement
Start Date: September 2022
Projected Completion Date:
February 2019
Completion
Date:
December 2023
Construction
Start Date: June 2024
Projected Completion Date:
June 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
Dag Hammarskjold Plaza, Manhattan
East 47th Street between First Avenue and Second Avenue
Community Board: 06
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024