La Guardia Playground Reconstruction Phase 1
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the sports courts and plaza (southern parcel) at La Guardia Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
October 2017
Completion Date:
September 2018
Procurement
Start Date: September 2018
Projected Completion Date:
June 2019
Completion
Date:
June 2019
Construction
Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date: October 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
La Guardia Playground, Brooklyn
Havemeyer Street, South 5th Street, Brooklyn Queens Expressway
Community Board: 01
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024