La Guardia Playground Reconstruction Phase 1

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the sports courts and plaza (southern parcel) at La Guardia Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: June 2019

Construction

Start Date: October 2019
Projected Completion Date: October 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $2,142,000
Funding Source: Mayoral

Location

La Guardia Playground, Brooklyn
Havemeyer Street, South 5th Street, Brooklyn Queens Expressway
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project