DeWitt Clinton Park Staircase Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the staircases in DeWitt Clinton Park.
Project Timeline
Design
Assigned & Start Date: May 2018
Projected Completion Date:
May 2019
Completion Date:
May 2019
Procurement
Start Date: May 2019
Projected Completion Date:
February 2020
Completion
Date:
February 2020
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: September 2021
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
De Witt Clinton Park, Manhattan
11th Avenue, 12th Avenue, West 52nd Street, West 54th Street
Community Board: 04
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024