DeWitt Clinton Park Staircase Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the staircases in DeWitt Clinton Park.

Project Timeline

Design

Assigned & Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: May 2019

Procurement

Start Date: May 2019
Projected Completion Date: February 2020
Completion Date: February 2020

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $1,613,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

De Witt Clinton Park, Manhattan
11th Avenue, 12th Avenue, West 52nd Street, West 54th Street
Community Board: 04

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024