Columbus Park Mulberry Street Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Mulberry Street entrance at Columbus Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2017
Projected Completion Date: May 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: June 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020
Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $467,000
Funding Sources:
  • City Council
  • Mayoral

Location

Columbus Park, Manhattan
Mulberry Street between Bayard and Mosco Streets
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project