Weeksville Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Weeksville Playground with new play equipment, seating and planting beds.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
October 2017
Completion Date:
November 2017
Procurement
Start Date: November 2017
Projected Completion Date:
August 2018
Completion
Date:
July 2018
Construction
Start Date: August 2018
Projected Completion Date:
August 2019
Completion Date: September 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Weeksville Playground, Brooklyn
Howard Avenue between Atlantic Avenue and Herkimer Street
Community Board: 03
Project Staff
Project Liaison: Davey Ives