Project Timeline
Design
Assigned & Start Date: November 2016
Projected Completion Date:
November 2017
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
July 2019
Completion
Date:
January 2020
Construction
Start Date: March 2020
Projected Completion Date:
September 2021
Completion Date: May 2022