Sternberg Park Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the synthetic turf field and construct new sports lighting at the basketball courts at Sternberg Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: February 2020

Construction

Start Date: October 2020
Projected Completion Date: October 2021
Completion Date: October 2021

Understand how we build parks.

Funding

Total Funding: $2,114,000
Funding Source: City Council

Location

Sternberg Park, Brooklyn
Montrose Avenue, Boerum Street, Lorimer Street, Leonard Street
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025