Sternberg Park Synthetic Turf Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the synthetic turf field and construct new sports lighting at the basketball courts at Sternberg Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2017
Projected Completion Date:
September 2018
Completion Date:
August 2018
Procurement
Start Date: August 2018
Projected Completion Date:
May 2019
Completion
Date:
February 2020
Construction
Start Date: October 2020
Projected Completion Date:
October 2021
Completion Date: October 2021
Understand how we build parks.
Funding
Funding Source: City Council
Location
Sternberg Park, Brooklyn
Montrose Avenue, Boerum Street, Lorimer Street, Leonard Street
Community Board: 01
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025