Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
December 2017
Completion Date:
December 2017
Procurement
Start Date: December 2017
Projected Completion Date:
September 2018
Completion
Date:
July 2018
Construction
Start Date: October 2018
Projected Completion Date:
April 2020
Completion Date: January 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Evelina Antonetty Playground, Bronx
Grand Concourse between East 144th Street and East 149th Street
Community Board: 01
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025