Playground 134 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Playground 134 with new basketball courts, play equipment, a skate park, adult fitness equipment, a spray shower, and swings.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: November 2017
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: December 2019

Construction

Start Date: January 2020
Projected Completion Date: April 2021
Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: $7,022,000
Funding Sources:
  • Mayoral
  • State

Location

Playground One Thirty Four CXXXIV, Bronx
East 133rd Street, St. Anns Place, East 134th Street, Cypress Avenue
Community Board: 01

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025