Playground 134 Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Playground 134 with new basketball courts, play equipment, a skate park, adult fitness equipment, a spray shower, and swings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
November 2017
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
July 2019
Completion
Date:
December 2019
Construction
Start Date: January 2020
Projected Completion Date:
April 2021
Completion Date: June 2021
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- State
Location
Playground One Thirty Four CXXXIV, Bronx
East 133rd Street, St. Anns Place, East 134th Street, Cypress Avenue
Community Board: 01
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025