Plimpton Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play equipment, swings, spray shower, seating, pavements, drainage systems, drinking fountain, fencing and entrance area at Plimpton Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2016
Projected Completion Date: December 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: October 2018

Construction

Start Date: November 2018
Projected Completion Date: November 2019
Completion Date: November 2019

Understand how we build parks.

Funding

Total Funding: $3,704,000
Funding Source: Mayoral

Location

Plimpton Playground, Bronx
Edward L. Grant Highway and Plimpton Avenue
Community Board: 04

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project