Plimpton Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play equipment, swings, spray shower, seating, pavements, drainage systems, drinking fountain, fencing and entrance area at Plimpton Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2016
Projected Completion Date:
December 2017
Completion Date:
January 2018
Procurement
Start Date: January 2018
Projected Completion Date:
October 2018
Completion
Date:
October 2018
Construction
Start Date: November 2018
Projected Completion Date:
November 2019
Completion Date: November 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Plimpton Playground, Bronx
Edward L. Grant Highway and Plimpton Avenue
Community Board: 04
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024