Almeda Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Almeda Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: May 2019

Construction

Start Date: July 2019
Projected Completion Date: September 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $7,179,000
Funding Source: Mayoral

Location

Almeda Playground, Queens
Beach Channel Drive between Beach 65th Street and Beach 66th Street
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project