Clawson Playground Reconstruction Phase I

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the area of Clawson Playground behind PS 50 with new play equipment, safety surfacing, benches and plantings.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: December 2019

Construction

Start Date: March 2020
Projected Completion Date: March 2021
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $2,411,000
Funding Sources:
  • Borough President
  • City Council

Location

Clawson Playground, Staten Island
Adelaide Avenue betweeen Elmira Street and Whitehall Street
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024