Clawson Playground Reconstruction Phase I
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the area of Clawson Playground behind PS 50 with new play equipment, safety surfacing, benches and plantings.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2017
Projected Completion Date:
April 2018
Completion Date:
October 2018
Procurement
Start Date: October 2018
Projected Completion Date:
July 2019
Completion
Date:
December 2019
Construction
Start Date: March 2020
Projected Completion Date:
March 2021
Completion Date: October 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Clawson Playground, Staten Island
Adelaide Avenue betweeen Elmira Street and Whitehall Street
Community Board: 03