Little Bush Park Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground at Little Bush Park.
Project Timeline
Design
Assigned & Start Date: April 2018
Projected Completion Date:
April 2019
Completion Date:
May 2019
Procurement
Start Date: May 2019
Projected Completion Date:
January 2020
Completion
Date:
January 2020
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: September 2021
Understand how we build parks.
Funding
Funding Source: City Council
Location
Nathan Weidenbaum Playground, Queens
Laurel Hill Boulevard between 63rd Street and 64th Street
Community Board: 02
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks