Ravenswood Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Ravenswood Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2018
Projected Completion Date:
January 2019
Completion Date:
February 2019
Procurement
Start Date: February 2019
Projected Completion Date:
November 2019
Completion
Date:
April 2021
Construction
Start Date: May 2021
Projected Completion Date:
May 2022
Completion Date: June 2022
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Ravenswood Playground, Queens
21st Avenue between 34th Avenue and 35th Avenue
Community Board: 01
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks