Ravenswood Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Ravenswood Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2018
Projected Completion Date: January 2019
Completion Date: February 2019

Procurement

Start Date: February 2019
Projected Completion Date: November 2019
Completion Date: April 2021

Construction

Start Date: May 2021
Projected Completion Date: May 2022
Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $6,500,000
Funding Sources:
  • Borough President
  • City Council

Location

Ravenswood Playground, Queens
21st Avenue between 34th Avenue and 35th Avenue
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project