Brookville Park Entrance Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct an entrance to Brookville Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2017
Projected Completion Date:
May 2018
Completion Date:
June 2018
Procurement
Start Date: June 2018
Projected Completion Date:
February 2019
Completion
Date:
February 2019
Construction
Start Date: July 2019
Projected Completion Date:
July 2020
Completion Date: October 2020
Understand how we build parks.
Funding
Funding Source: City Council
Location
Brookville Park, Queens
147th Avenue and Brookville Boulevard
Community Board: 13
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project