Brookville Park Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct an entrance to Brookville Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: February 2019
Completion Date: February 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $1,148,000
Funding Source: City Council

Location

Brookville Park, Queens
147th Avenue and Brookville Boulevard
Community Board: 13

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024