Sunset Cove Park Boardwalk and Outdoor Classroom Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a boardwalk and outdoor classroom at Sunset Cove Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2016
Projected Completion Date: January 2018
Completion Date: May 2021

Procurement

Start Date: May 2021
Projected Completion Date: February 2022
Completion Date: March 2022

Construction

Start Date: May 2022
Projected Completion Date: May 2023
Completion Date: August 2023

Understand how we build parks.

Funding

Total Funding: $4,242,000
Funding Sources:
  • Borough President
  • Federal
  • Mayoral
  • State

Location

Sunset Cove Park, Queens
Cross Bay Boulevard between West 19th Road and West 22nd Road
Community Board: 14

 

Project Staff

Contact NYC Parks about this project

Last updated: 01/17/2025