Flushing Meadows Corona Park Henry Hudson Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Henry Hudson entrance at Flushing Meadows Corona Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: March 2019

Construction

Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $3,262,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park, Queens
111th Street between 53rd Avenue and 56th Avenue
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024