Pulaski Park Sport Courts Reconstruction and Tot Lot Construction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the sport courts and construct a tot lot in Pulaski Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
July 2018
Completion Date:
April 2019
Procurement
Start Date: April 2019
Projected Completion Date:
January 2020
Completion
Date:
February 2020
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: July 2021
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Pulaski Park, Bronx
Bruckner Boulevard between Willis Avenue and Brown Place
Community Board: 01
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024