Flushing Meadows Corona Park Garage Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the Parks Maintenance and Operations garage in Flushing Meadows Corona Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2016
Projected Completion Date:
August 2017
Completion Date:
September 2018
Procurement
Start Date: September 2018
Projected Completion Date:
June 2019
Completion
Date:
June 2019
Construction
Start Date: June 2020
Projected Completion Date:
December 2021
Completion Date: May 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park, Queens
Between Roosevelt Avenue and the Long Island Rail Road yard
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project