Flushing Meadows Corona Park Garage Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Parks Maintenance and Operations garage in Flushing Meadows Corona Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2016
Projected Completion Date: August 2017
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019
Completion Date: June 2019

Construction

Start Date: June 2020
Projected Completion Date: December 2021
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $7,094,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park, Queens
Between Roosevelt Avenue and the Long Island Rail Road yard
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025