Public Place Mall Paving Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Public Place Mall.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: June 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: June 2018

Construction

Start Date: April 2019
Projected Completion Date: April 2020
Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $556,000
Funding Source: City Council

Location

Public Place, Brooklyn
Eldert Lane, Liberty Avenue, and Glenmore Avenue
Community Board: 05

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025