Manhattan Beach Promenade Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the promenade pavements, concrete steps and benches and plant trees at Manhattan Beach Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2016
Projected Completion Date: September 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: September 2019

Construction

Start Date: September 2019
Projected Completion Date: May 2021
Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $2,679,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Manhattan Beach Park, Brooklyn
Oriental Boulevard between Ocean Avenue and Mackenzie Street
Community Board: 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025