Sunset Park Path Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct stairs, handrails and landings in Sunset Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
October 2017
Completion Date:
August 2018
Procurement
Start Date: August 2018
Projected Completion Date:
May 2019
Completion
Date:
September 2019
Construction
Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date: October 2020