J.J. Byrne Playground Synthetic Turf Lawn Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a panel of synthetic turf lawn at J.J. Byrne Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
June 2017
Completion Date:
July 2017
Procurement
Start Date: July 2017
Projected Completion Date:
April 2018
Completion
Date:
June 2018
Construction
Start Date: October 2018
Projected Completion Date:
October 2019
Completion Date: March 2019