J.J. Byrne Playground Synthetic Turf Lawn Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a panel of synthetic turf lawn at J.J. Byrne Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: June 2017
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018
Completion Date: June 2018

Construction

Start Date: October 2018
Projected Completion Date: October 2019
Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $169,000
Funding Sources:
  • City Council
  • Mayoral

Location

Washington Park, Brooklyn
5th Avenue between 3rd Street and 4th Street
Community Board: 06

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024