Marine Park Gerritsen Avenue Pedestrian Path Construction Phase 2
-
100% complete
-
100% complete
-
100% complete
This project will construct a new asphalt path, benches and accessible entrances adjacent to the Gerritsen Avenue ballfields in Marine Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2016
Projected Completion Date:
June 2017
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
February 2018
Completion
Date:
March 2019
Construction
Start Date: June 2019
Projected Completion Date:
June 2020
Completion Date: October 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
- State
Location
Marine Park, Brooklyn
Gerritsen Avenue near Florence Avenue and Channel Avenue
Community Board: 15, 18
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project