Marine Park Gerritsen Avenue Pedestrian Path Construction Phase 2

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new asphalt path, benches and accessible entrances adjacent to the Gerritsen Avenue ballfields in Marine Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2016
Projected Completion Date: June 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: February 2018
Completion Date: March 2019

Construction

Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $696,000
Funding Sources:
  • City Council
  • Mayoral
  • State

Location

Marine Park, Brooklyn
Gerritsen Avenue near Florence Avenue and Channel Avenue
Community Board: 15, 18

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024