Hugh Grant Circle and Virginia Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Virginia Park and Hugh Grant Circle, including general site work, pavements, fencing, curbs, lighting and landscaping.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: July 2019

Construction

Start Date: September 2019
Projected Completion Date: March 2021
Completion Date: May 2021

Understand how we build parks.

Funding

Total Funding: $9,024,000
Funding Source: Mayoral

Locations

  • Hugh J. Grant Circle, Bronx
    East 177 Street, Westchester Avenue, Virginia Avenue
    Community Board: 09
  • Virginia Park, Bronx
    White Plains Road, Westchester Avenue, Cross Bronx Expressway
    Community Board: 09
 