Van Cortlandt Park Broadway Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the entrance to Van Cortlandt Park at Broadway and West 242nd Street.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2016
Projected Completion Date: November 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: January 2019

Construction

Start Date: March 2019
Projected Completion Date: June 2020
Completion Date: June 2020

Understand how we build parks.

Funding

Total Funding: $5,446,000
Funding Source: Mayoral

Location

Van Cortlandt Park, Bronx
Broadway at West 242nd Street
Community Board: 07, 08, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024