Susan Smith McKinney Steward Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play equipment, swings, and spray shower and construct a new adult fitness area, a multi-purpose synthetic turf field with a performance stage, benches, fences, drainage, water supply and planting at Susan Smith McKinney Steward Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: June 2019

Procurement

Start Date: June 2019
Projected Completion Date: March 2020
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: April 2022
Completion Date: August 2022

Understand how we build parks.

Funding

Total Funding: $6,999,000
Funding Source: Private

Location

Susan Smith McKinney Steward Park, Brooklyn
Jay Street, York Street, Bridge Street, Prospect Street
Community Board: 02

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024