McGolrick Park Paths Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the asphalt paths, benches and damaged sidewalks at McGolrick Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2016
Projected Completion Date:
April 2017
Completion Date:
November 2020
Procurement
Start Date: November 2020
Projected Completion Date:
August 2021
Completion
Date:
April 2022
Construction
Start Date: June 2022
Projected Completion Date:
June 2023
Completion Date: December 2022
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Msgr. McGolrick Park, Brooklyn
Nassau Avenue, Monitor Street, Russell Street, Driggs Avenue
Community Board: 01
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024