Jackie Robinson Park Reconstruction (M014-117M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct stairways, fencing, sidewalks, and entrances in Jackie Robinson Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
October 2017
Completion Date:
December 2017
Procurement
Start Date: December 2017
Projected Completion Date:
September 2018
Completion
Date:
August 2018
Construction
Start Date: October 2018
Projected Completion Date:
January 2020
Completion Date: May 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Jackie Robinson Park, Manhattan
West 145th Street, West 155th Street, Edgecombe Avenue, Bradhurst Avenue
Community Board: 09, 10
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025