Jackie Robinson Park Reconstruction (M014-117M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct stairways, fencing, sidewalks, and entrances in Jackie Robinson Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: August 2018

Construction

Start Date: October 2018
Projected Completion Date: January 2020
Completion Date: May 2020

Understand how we build parks.

Funding

Total Funding: $4,358,000
Funding Source: Mayoral

Location

Jackie Robinson Park, Manhattan
West 145th Street, West 155th Street, Edgecombe Avenue, Bradhurst Avenue
Community Board: 09, 10

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project