Colucci Playground Adult Fitness Equipment Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct an adult fitness area in Colucci Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2017
Projected Completion Date: December 2017
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: November 2018

Construction

Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $959,000
Funding Sources:
  • City Council
  • Mayoral

Location

Colucci Playground, Bronx
Wilkinson Avenue between Hutchinson River Parkway East and Mayflower Avenue
Community Board: 10

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025