Colucci Playground Adult Fitness Equipment Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct an adult fitness area in Colucci Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2017
Projected Completion Date:
December 2017
Completion Date:
January 2018
Procurement
Start Date: January 2018
Projected Completion Date:
October 2018
Completion
Date:
November 2018
Construction
Start Date: May 2019
Projected Completion Date:
May 2020
Completion Date: August 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Colucci Playground, Bronx
Wilkinson Avenue between Hutchinson River Parkway East and Mayflower Avenue
Community Board: 10
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project