Faber Park Active Recreation, Lighting and Seating Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct new active recreation areas, paths, seating, lighting and an expanded public gathering area at Faber Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018
Completion Date: April 2019

Construction

Start Date: April 2019
Projected Completion Date: October 2020
Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $5,412,000
Funding Sources:
  • City Council
  • Mayoral

Location

Faber Pool and Park, Staten Island
2175 Richmond Terrace, between Faber Street and Sharpe Avenue
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 02/21/2025