Faber Park Active Recreation, Lighting and Seating Area Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct new active recreation areas, paths, seating, lighting and an expanded public gathering area at Faber Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
October 2017
Completion Date:
March 2018
Procurement
Start Date: March 2018
Projected Completion Date:
December 2018
Completion
Date:
April 2019
Construction
Start Date: April 2019
Projected Completion Date:
October 2020
Completion Date: November 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Faber Pool and Park, Staten Island
2175 Richmond Terrace, between Faber Street and Sharpe Avenue
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project